For the first time in the country's history, nuclear power has been supplied to the national grid, with 350 megawatts of electricity from Unit 1 of the Rooppur Nuclear Power Plant connected to the grid on a trial basis at 3:16pm on Tuesday.
Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant Construction Project and chief scientific officer of the Bangladesh Atomic Energy Commission (BAEC), told Daily Waadaa that the trial operation phase would begin after the initial test supply is completed.
"Under the agreement with the Russian contractor, Unit 1 will begin commercial electricity supply at its full capacity of 1,200 megawatts after completing 10 months of trial operation," he said.
Science and Technology Minister Fakir Mahbub Anam Swapan, MP, was present during the grid connection, which officials described as a significant milestone for the country's first nuclear power plant.
Under the scheduled plan, electricity generated during the initial trial connection will be supplied to the national grid for around eight to 10 hours.
During this period, engineers will conduct technical tests to assess the performance and stability of the plant's turbine, generator and integrated operating system in coordination with the national grid.
The plant will then be disconnected from the grid for further technical assessments. After a break of around 28 hours, it will be reconnected for another four to six hours to complete the necessary technical and operational tests.
If the results of the tests are satisfactory and all scheduled work for this phase is completed, the plant will require approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) to proceed to the next stage of trial operation.
Subject to regulatory approval, the plant will again be connected to the national grid on a trial basis to continue the process.
The two units of the Rooppur Nuclear Power Plant are expected to generate a combined 2,400 megawatts of electricity, with each unit having a capacity of 1,200 megawatts.